Bitcoin mining farm construction combines industrial electrical engineering, HVAC design, civil construction, and data centre operations. Coinfast has built facilities across Russia, Xinjiang, and Paraguay — 1MW modules to 100MW+ greenfields. Here is what we have learned.
Site Selection: The Irreversible Decisions
Power availability is the first criterion — not just current capacity, but ability to deliver at scale over 5–10 years. Regulatory stability matters equally. Climate is the third variable: cold-climate sites deliver passive cooling advantages that reduce HVAC capex for the entire facility lifetime.
Power Infrastructure Design
At 10MW+, transformer procurement is the most common construction bottleneck — lead times of 6–12 months are standard. Natural gas generation integration should be designed in from the start, not retrofitted.
Cooling System Selection
- Air cooling: Lowest cost, widest compatibility, best in cold climates
- Immersion: 20–30% efficiency improvement, higher infrastructure cost
- Hydro/liquid: Best for new high-density machines, requires dedicated plumbing